Join Our Official Whatsapp Group

PIPILINE ON-BOTTOM STABILITY ANALYSIS REPORT

INTRODUCTION
General

The AFANG field is located in block-00 OML 419, approximately 45 km of the south-eastern coast of Wakanda in approximately 40 meters water depth. The field, initially brought into production in 1997 is owned by the Joint Venture APC/PDP and is operated by APPDPLPC Nigeria Limited (APPDPLPCNL). The OML 419 block is shown in the following figure.

Pipe line routes

Figure 1-1: Project Scope

Figure 1‑2: AFANG Field Architecture

1.2           Objective

The objective of this document is to confirm adequacy for use, the already selected pipeline concrete weight coating thickness for the 12-inch APC-2 to PDP-1 Crude Export Line.

The line pipe has been coated with 2.7mm 3LPP coating, as well as 30mm concrete weight coating.

1.3           Definitions and Abbreviations                        
Definition
Company APPDPLPC Nigeria Limited
Contractor Global Oceon Nig. LTD
Supplier The Party including its employees, agents, inspectors and other

authorized representatives Contracted by the Company/ Contractor to carry out the Procurement, Construction Installation and Commissioning activities on the Project

Shall Indicates mandatory requirement
Should Indicates preferred recommendation

Table 1-1: Definitions

1.4   Abbreviations                      Table 1-2: Abbreviations

Abbreviation Definition
API American Petroleum Institute
APS Application Procedure Specification
ASME American Society of Mechanical Engineers
CA Corrosion Allowance
CP Cathodic Protection
DNV Det Norske Veritas
DP Dynamic Positioning
3LPP 3-Layer Polypropylene
FJ Field Joint
FJC Field-Joint Coating
FOS Factor of Safety
HRC Hardness Rockwell C Scale
ID Inner Diameter
LAT Lowest Astronomical Tide
OD Outside Diameter
SG Specific Gravity
SMYS Specified Minimum Yield Strength
WT Wall Thickness
1.5    References
1.5.1          Conflict of Information

Where conflict occurs between the requirements of this specification and referenced Codes and Standards, the CONTRACTOR shall notify the COMPANY in writing immediately for resolution. In the absence of such a statement, full compliance with the order of precedence below shall be assumed.

The order of precedence for the documents shall be as follows:

  • Nigerian National Regulations Standards
  • Project Specification
  • International Codes and Standards

Where there are conflicts of interpretation, the principal will review to determine what should apply.

 

1.5.2 Project Documents

REF. DOC No DOCUMENT TITLE REV.
[R1] LP-NG-HCD2023-RPT-018 Wall Thickness Calculation Report 1
[R2] LP-NG-HCD2023-RPT-017 Pipeline Design Basis 2

Table 1-3: Reference and Document

 

1.5.3 Codes and Standards

REF. DOCUMENT NUMBER DOCUMENT TITLE REV.
[R3] DNVGL-RP-F109 On-bottom stability design of submarine pipelines

Table 1-4: Codes and Standards

 

2                     SUMMARY AND CONCLUSION
2.1    Summary

The on-bottom stability analysis has been assessed for the 12-inch APC-2 to PDP-1 Crude Export Line and the conservative absolute static stability requirement was considered as per DNVGL-RP F109. The Table 2-1 summarizes the results of the on-bottom stability calculations.

Table 2-1: Absolute Stability Results for Significant Wave Height and Bottom Current Extremes

Flowline Load Case Condition Concrete Weight Coating Thickness Calculated Absolute Stability FOS Allowable FOS SG

 

Remark
Horizontal Vertical
12-inch APC-2 to PDP-1 Crude Export Line Installation (empty) 1yr wave, 10yr Current  

 

 

 

 

30mm

1.12 5.78  

 

 

 

 

1

1.66 Satisfies the DNVGL-RP-F109 absolute static stability requirements.

 

10yr wave, 1yr Current 1.44 7.55
Hydrotest 1yr wave, 10yr Current 1.43 7.19 1.96
10yr wave, 1yr Current 1.84 9.36
Operation (Corroded Case) 100yr wave ,10yr current 1.01 4.52 1.64
10yr wave, 100yr current 1.06 4.72

Note:

(1) The specific gravity is the ratio of empty weight in the air to buoyancy and must be greater than 1.15 to satisfy the on-bottom stability requirements.

(2) The factor of safety (FOS) must exceed 1.0 to meet the DNVGL-RP-F109 absolute static stability requirements.

2.2   Conclusion

It is confirmed that the already selected concrete weight coating thickness of 30mm is adequate and satisfies the DNVGL-RP-F109 absolute static on-bottom stability requirement.

 

3           DESIGN BASIS
3.1        Pipeline Design Data

The table below detail parameters used in the calculation spreadsheet attached.

Table 3‑1: Pipeline Characteristics

Parameters Units Values
Pipe Steel Outer Diameter (OD) Inch (mm) 12.75 (329.3)
  Pipe Wall thickness mm 12.7
   Design Pressure Barg 144.0
Design Temperature (0C) 80
Pipe Grade                API 5L X65
SMYS MPa                     448
SMTS Mpa 531
Corrosion Allowance mm 3
Steel Poisson Ratio 0.3
Single Joint Length m 12.2
Anti-Corrosion Coating Thickness mm 2.7
Concrete Coating Thickness mm 30
Concrete Coating Poisson Ratio 0.2
3.2                Material Densities

The following material densities are used for the pipeline upheaval buckling analysis.

Table 3‑2: Material Properties

Material Density (kg/m3) Youngs Modulus (Mpa)
Steel 7850 207000
Anti-corrosion Coating 1442  
Concrete Weight Coating 3044  
Seawater 1030  

 

3.3    Content Specific Gravity

The content specific gravity is 0.19.

3.4    Soil Data

The following soil data taken from the Pipeline Design Basis [Ref.R2] are used in the analysis.

Table 3-3: Soil Data

Parameters Units Values
Seabed Soil Type Clay
Bulk Unit Weight kN/m3 18
Submerged Unit Weight kN/m3
  Undrained Shear Strength, Cu kPa 4.90

 

3.5    Environmental Data
3.5.1           Water Depth

The following environmental data taken from the Pipeline Design Basis [Ref.R2] are used in the analysis.

Table 3-4: Water Depth

 

Pipeline

Water Depth (LAT)

(m)

Minimum Maximum
12-inch APC-2 to PDP-1 Crude Export Line 40.0 40.0

 

3.5.2           Wave and Current Data

Wave and current data along the pipeline routes are extracted from the Pipeline Design Basis [Ref.R2] as shown below.

Table 3-5: Significant Wave Height and Associated Current

Table 3-6: Bottom Current Extremes

Table 3-7: Wave and Wave Associate with Steady Current Extremes

3.6    Marine Growth

The table below provides growth estimates

Table 3-8: Marine Growth Thickness 

 

4         DESIGN METHODOLOGY
4.1      Design Life

The on-bottom stability analysis was based on the absolute static stability criteria set out in                            DNVGL-RP-F109. In-house spreadsheet has been used for the on-bottom stability analysis.

The analysis was performed considering a minimum water depth of 40m which represents the                worst-case scenario. The effects of the wave induced velocity along the pipelines are insignificant at       this water depth. The stability requirements for the pipeline were determined for installation, hydrotest and operation conditions.

The submerged weight of the pipelines satisfies the On-bottom stability requirements of                                   DNVGL RP F109. A pipeline can be considered to satisfy the absolute static stability requirement if:

 

  • Lateral Stability check

 

 

  • Vertical Stability check

 

Where;

Ysc :         Safety Factor

Ws :        Submerged weight of the line (N/m)

µ  :         Soil friction factor

Fy  :         Peak Horizontal force (N/m)  eq. 3.40 in DNVGL-RP-F109

FZ :         Peak vertical force (N/m)  eq. 3.41 in DNVGL-RP-F109

Fr  :         Passive Resistance Force (N/m)

4.2    Assumption

The following assumptions have been made:

  • Flat Seabed.
  • Minimum water depth has been conservatively considered for the pipeline stability analysis.
  • Environmental loading is assumed to act perpendicularly to the pipeline (i.e. θc = 90°).
  • Minimum content density has been considered for the operating conditions for the production line as the worst-case scenario.
  • The most conservative coefficient of friction (µ=0.2) has been used in this analysis.
  • Pipeline penetration and trenching was not considered.
  • Marine growth was not considered for hydrotest and installation cases.
  • Additional weight due to anodes or any other miscellaneous Pipeline appurtenances are considered as negligible.
4.3                Load Cases

The following load cases had been assessed:

Table 4-1: Load Cases

Condition Analysis Water Depth Sig. Wave Height Peak Period Current Content Corrosion allowance Marine Growth
Installation Minimum Water depth along the Route w.r.t LAT 1year 1year 10year Empty 3 mm 0 mm
10year 10year 1year
Hydrotest Minimum Water depth along the Route w.r.t LAT 1year 1year 10year Water      3 mm 0 mm
10year 10year 1year
Operation

(Corroded Case)

Minimum Water depth along the Route w.r.t LAT 10year 10year 100year Crude      2.7 mm 59 mm
100year 100year 10year

 

5        RESULT

The result of the concrete weight coating check for 12-inch APC-2 to PDP-1 Crude Export Line is presented in the Table 5-1 below. See calculation spreadsheet in appendix 1.

Table 5-1: Results Summary

Flowline Load Case Condition Concrete Weight Coating Thickness Calculated Absolute Stability FOS Allowable FOS SG

 

Remark
Horizontal Vertical
12-inch APC-2 to PDP-1 Crude Export Line Installation (empty) 1yr wave, 10yr Current  

 

 

 

 

30mm

1.12 5.78  

 

 

 

 

1

1.66 Satisfies the DNVGL-RP-F109 absolute static stability requirements.

 

10yr wave, 1yr Current 1.44 7.55
Hydrotest 1yr wave, 10yr Current 1.43 7.19 1.96
10yr wave, 1yr Current 1.84 9.36
Operation (Corroded Case) 100yr wave ,10yr current 1.01 4.52 1.64
10yr wave, 100yr current 1.06 4.72